Crane deployed in SSH ambulance bay starting at 6 a.m. on Sunday, November 13
On Sunday, November 13, a crane will be deployed in the ambulance bay from 6 a.m. to 3 p.m. The crane is required to remove a temporary air handling unit and equipment from the roof.
Impact:
· Alternate ambulance access established (see below).
· Limited ambulance bay parking will be available.
· All ambulance traffic will use alternate access to the South parking lot for patient drop-off and pick-up.
· Pedestrian and vehicle traffic will be modified in the work zone.
Mitigation:
· Weymouth Police and Public Safety details will be present to assist with access and direct ambulance traffic.
· Directional signage and traffic barriers will be installed.
· South parking lot designated area for patient drop-off and pick-up.
· A crane lift plan was established.
· An Interim Life Safety Measure Assessment and Pre-Construction Risk Assessment will be conducted.
· Work and fall zones will be identified and secured with safety cones and caution tape.
· Crane spotter will be assigned to the ground for safety and to direct crane activities.